Dealing with a deck that has settled unevenly can be a frustrating challenge. When concrete footings sink into the soil, the entire load path of the deck is compromised, leading to sloping surfaces and stressed structural connections. While completely replacing severely sunken or undersized footings is sometimes necessary, minor settlement issues can often be resolved by raising the existing footing back to its proper elevation.
Evaluating The Sinking Footing
Before beginning any structural lifting, you must assess the condition of the footing and its connection to the deck structure. This repair method is most effective for smaller, intact concrete footings that have simply settled due to soil compression.
If the footing is cracked, degraded, or fundamentally undersized for the load it carries, raising it will only be a temporary fix. Furthermore, you must verify that the supporting post is securely attached to both the deck beam above and the concrete footing below using heavy-duty, code-approved structural hardware.
Excavation And Preparation
The first step is to carefully remove the soil around the perimeter of the concrete block. Dig down alongside the footing, angling the excavation outward to give yourself comfortable working room. The goal is to clear the sides to reduce soil friction, allowing the footing to move upward freely.
Do not dig directly beneath the footing at this stage. Keep the soil undisturbed directly under the concrete to maintain a solid base for the lifting process. Depending on the deck's height and access, you may need to temporarily remove some deck boards to safely operate your tools and jacks.
Safe Jacking And Lifting Procedures
Position a heavy-duty hydraulic jack under a primary structural member, such as a supporting beam or a reinforced rim joist. If the deck post is properly secured to the footing with strong metal hardware, lifting the beam will pull the footing up along with it.
Raise the structure slowly and in small increments. Listen carefully for any sounds of hardware stressing or wood splitting. Always place solid wooden blocking or cribbing under the beam as you lift. Never rely solely on a hydraulic jack to hold the weight of a deck. If the jack fails, the blocking will catch the load and prevent a catastrophic collapse.
Proper Base Preparation And Backfilling
Once the footing is raised to the correct elevation and fully supported by temporary blocking, you must fill the newly created void beneath the concrete. While screened soil or sand can technically fill the space, crushed structural gravel is vastly superior, as it compacts tightly and resists washing out over time. Never place your hands or fingers underneath the suspended footing.
Always use a long handled tool, such as a shovel or a sturdy piece of lumber, to pack the fill material tightly under the concrete block. Once the void is completely packed and the footing is resting on a solid base, slowly lower the jack. Finally, backfill the perimeter excavation, compact the soil, and ensure the surrounding grade slopes away from the footing for proper drainage.
Three Key Tips
Ensure Positive Hardware Connections: Before attempting to lift a footing by jacking the deck beam, verify that the post is secured to the concrete with a structural post base (such as an anchor bracket) and secured to the beam above with appropriate post cap hardware. Relying on gravity alone or simple toenailing will cause the deck framing to separate from the post during the lift.
Use Structural Fill Material: When packing material beneath the newly raised footing, avoid using loose dirt or fine sand, which can compress or wash away during heavy rains. Instead, use a compactable crushed stone or angular gravel base. This meets standard structural practices by providing a stable, self-compacting layer that distributes the load evenly to the underlying soil.
Prioritize Jacking Safety With Cribbing: Never put any part of your body underneath a supported load. As you raise the deck, continuously stack solid wood blocks (cribbing) adjacent to the jack. This ensures that if the jack slips, loses hydraulic pressure, or shifts, the deck will only drop a fraction of an inch onto the blocks, preventing severe injury.
Bonus Questions And Answers
While raising a settled footing is a practical solution for minor subsidence, understanding the structural science behind deck foundations can prevent future issues.
Why Do Deck Footings Sink In The First Place?
Footings typically settle because the soil beneath them cannot adequately support the structural load of the deck. According to the International Residential Code (IRC), footings must bear on undisturbed natural soil or engineered, properly compacted fill. If a footing was originally poured over loose topsoil, decomposing organic matter, or poorly compacted backfill, the weight of the deck will eventually compress the earth, causing the footing to sink. Proper water drainage is also critical, as saturated soil loses its load bearing capacity.
Can I Pack Wet Concrete Under The Raised Footing Instead Of Gravel?
Yes, underpinning the raised footing with concrete is an excellent, permanent solution. Once the deck is securely jacked and temporarily supported by secondary blocking, you can pack a stiff mix of high-strength concrete or non-shrink structural grout into the void beneath the suspended block. This method ensures a perfectly contoured, solid transfer of the structural load to the undisturbed soil below, minimizing the risk of future settlement.
Does The Frost Line Affect Deck Footing Depth?
Yes, in colder climates, the frost line plays a major role in footing stability. Building codes require footings to extend below the local frost depth to prevent frost heave. When water in the soil freezes, it expands, pushing upward with immense force. If a footing does not extend below this freeze zone, the expanding ice will lift the deck in the winter, and the structure will sink unevenly when the ground thaws in the spring. Always consult local municipal codes for exact frost depth requirements in your region.