Home Building And Repairs

How To Install Roofing Shingles Under Fascia Board And Roof Overhang - Roof Under Roof Valley

Mastering Tight Roof Transitions With Composition Shingles

Roofing a section of a house where a lower roofline tucks beneath the fascia and rafters of an upper section presents a unique waterproofing challenge. Successfully routing water away from these cramped junctions requires precise layering of flashing, underlayment, and composition shingles. By systematically opening up the work area and staggering your materials correctly, you can create a resilient, code-compliant roof transition that prevents long-term moisture damage.

Preparation And Sheathing Removal

Attempting to slide flashing and shingles blindly underneath an existing overhanging fascia is a common mistake that often leads to compromised waterproofing. The most effective approach is to temporarily remove the lowest section of roof sheathing on the upper roof structure. Opening this cavity provides the critical access needed to securely fasten edge metals and route underlayment properly. Before closing this area back up later, any exposed wood rafters or the underside of the sheathing that will become permanently inaccessible should be painted or sealed to protect against future moisture exposure.

Metal Flashing Assembly

Proper water management begins with a layered flashing system. Once the sheathing is removed and the roof edge metal is secured, a 1x4 nailer or fascia board is installed, notched as needed to accommodate the surrounding metal profiles. A three-by-three-inch L-metal flashing is then integrated into the corner transition, topped by a Z-bar flashing custom-cut to fit the specific roof pitch. Nailing should be kept to an absolute minimum in the primary water channel. Fasteners should only be placed high up on the flashing metals where water is least likely to penetrate, spacing them out every four feet along the top edges.

Underlayment And Weatherproofing

With the metal flashing in place, the roofing paper or synthetic underlayment is rolled out directly over the metal edges. Building codes and manufacturer instructions dictate that underlayment must be lapped sequentially so that the upper layers always overlap the lower layers, ensuring water flows freely down the roof slope without catching an open seam.

When working inside a roof valley or transition, the underlayment from the adjacent slopes must be woven or overlapped generously to create a highly water-resistant barrier. Fasten the underlayment firmly, but avoid excessive stapling or nailing, as the shingle fasteners will ultimately secure the entire assembly.

Installing The Shingles And Finalizing The Sheathing

The roofing process begins with a starter course applied at the eave. The shingles are then installed row by row, maintaining proper horizontal staggering between joints according to the manufacturer's specified minimums, which is usually around five and a half to six inches. As you weave the shingles up into the transition area, pay close attention to course exposure.

Variations in roof overhang dimensions can sometimes throw off the standard six-inch reveal, requiring careful layout adjustments. Finally, when reinstalling the upper roof sheathing over the newly shingled section, the wood must be trimmed back slightly. The sheathing should never rest directly on top of the asphalt shingles, as this restricts water flow and causes the wood to wick moisture.

Three Key Construction Tips

Pre-paint inaccessible framing. Always apply primer and paint to the underside of sheathing and exposed rafters inside tight roof cavities before fastening the roof deck back in place, as you will not be able to reach these areas for future maintenance.

Limit starter course overhang. Extend the starter strip and the first course of composition shingles no more than a half-inch past the drip edge. Extending the shingles further makes them highly susceptible to bending, cracking, and wind damage.

Prevent sheathing-to-shingle contact. When replacing the upper roof deck over a lower shingled section, cut the plywood or OSB sheathing back so it hovers above the roof surface. Direct contact traps debris and causes the wood to rot from water wicking up the grain.

Frequently Asked Questions

Beyond the foundational steps of blending intersecting rooflines, proper water management requires a thorough understanding of building code applications.

Why Is Kickout Flashing Required Where A Lower Roof Eaves Meets A Vertical Wall?

According to the International Residential Code, flashing must be installed to divert water away from where the eave of a sloped roof intersects a vertical sidewall. Kickout flashing is a specialized, angled piece of metal installed at the very bottom of the step flashing run. It catches the heavy volume of water rushing down the roof-to-wall intersection and forcibly kicks it outward into the gutter. Without this critical component, water bypasses the gutter and runs directly down the exterior siding, frequently causing severe rot inside the wall cavity.

Should The Roofing Underlayment Go Over Or Under The Drip Edge Metal?

The placement of underlayment relative to the drip edge depends entirely on which edge of the roof you are working on, a rule designed to mimic the natural flow of gravity. Along the lower eave of the roof, the drip edge metal is installed first, directly against the bare roof deck, and the underlayment is layered over the top of it. Along the rake or the sloped sides of the gable, the underlayment is installed first, and the drip edge metal is fastened over the top of the underlayment. This specific overlapping method prevents wind-driven rain from getting beneath the underlayment on the sides, while ensuring water freely sheds off the bottom eave.

How Many Fasteners Are Required Per Composition Shingle To Meet Building Codes?

The standard fastening schedule for a traditional architectural asphalt shingle requires a minimum of four roofing nails per shingle, placed precisely on the manufacturer-designated nail line. However, in regions prone to high winds or extreme weather events, building codes and manufacturers mandate a high-wind fastening schedule, which increases the requirement to six nails per shingle. The nails must penetrate completely through the roofing material and extend a minimum of three-quarters of an inch into the roof sheathing to provide adequate withdrawal resistance against wind uplift.

Back To Roofing

Our Favorite Construction Books
Stair Building Tutorials
Find Out How Do It Yourselfer’s Like You Can Become Great Stair Builders.
20x24 Garage And Loft
Learn How To Build A Variety of Different 2 Car Garages With Lofts.
Home Addition Projects
Do It Yourself Building Ideas for Small Budget One Story or Large Second Story Room Additions
Two Bedroom Home Build
Check Out This Small Home Building Project That A Small Family Like Yours Might Appreciate.
1923 Old Home Framing Project
Let’s Take A House Journey Back In Time To Learn More About Old House Construction.
434 Square Feet Home Building Project
Find Out How You Can Build This Small Cottage Style House or Backyard Granny Flat.
Two Story Open Floor Plan Project
Another Great Home Building Project That Could Provide Exactly What You Need in Your Next Home.
L Shaped Floor Plan Building Project
Check Out Our First Home Building Project To Get More Ideas About New House Construction.
Bathroom Remodeling
Check Out Our Helpful Videos Before Your Next Remodel to Avoid Making Dumb Mistakes.
Building Foundations
Learn How to Design and Build Foundations for A House or A House on The Side of a Hill.
Learn More About Decks
More Educational Deck BuildingTutorials That Save Time And Money.
Easy To Build Green House
This is One of The Easiest Green House or Shed You Can Possibly Build.
Framing Education
Learn More About Wall, Ceiling, Floor And Roof Framing.
Plumbing Repairs
Learn How To Fix Your Own House Plumbing.
Crawlspace Repairs
Watch Our Tutorials if You Need To Replace A Wood Beam or Sagging Floor Joist.
Framing Repairs
We've Got You Covered From Termites To Wood Rot And From Top To Bottom.